Strengthening Borders at the Port of Trois-Rivières
Federal contribution
$756,260
Federal share46%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedNov 2, 2009
20102011
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Trois-Rivières Port Authority
- Construction start
- Aug 1, 2010(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Sep 1, 2010
Also in Trois-Rivières
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29328 in the federal list. How to read these figures.