Lucille Mountain Forest Service Road Bridge Replacement
Federal contribution
$56,345
Federal share42%
of $135.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedApr 7, 2009
ApprovedJan 28, 2010
2010
Built
Approved 10 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Jul 15, 2010(actual)
- Construction end
- Nov 15, 2010(actual)
Against the original forecast
- Construction start7 weeks earlyforecast Sep 1, 2010
- Construction end2 weeks lateforecast Oct 30, 2010