Water Metering and Conservation

McBride, British Columbia

completeDrinking WaterISF
Federal contribution
$125,000
Federal share33%

of $375.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 13, 2009
ApprovedSep 1, 2009
20102011
Built

Approved 6 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Village of McBride
Construction start
Oct 25, 2009(actual)
Construction end
Oct 24, 2011(actual)

Against the original forecast

  • Construction start4 months lateforecast Jul 1, 2009