Dominion Creek Drinking Water Intake Replacement
Federal contribution
$172,012
Federal share50%
of $344.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of McBride
- Construction start
- Sep 14, 2017(actual)
- Construction end
- Oct 5, 2018(actual)
Against the original forecast
- Construction start5 weeks lateforecast Aug 8, 2017
- Construction end5 weeks lateforecast Aug 30, 2018
Also in McBride
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49838 in the federal list. How to read these figures.