Bowker Creek Greenway - Phase 1

Saanich, British Columbia

completeActive TransportationISF
Federal contribution
$113,630
Federal share24%

of $470.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 13, 2009
ApprovedAug 10, 2009
201020112012
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
District of Saanich
Construction start
Apr 1, 2009(actual)
Construction end
Dec 23, 2011(actual)

Against the original forecast

  • Construction start3 months earlyforecast Jul 1, 2009
  • Construction end3 months lateforecast Sep 30, 2011