Federal contribution
$18,000
Federal share25%
of $72.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 13, 2009
ApprovedAug 10, 2009
Built
Approved 5 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Smithers
- Construction start
- Jul 13, 2009(actual)
- Construction end
- Sep 4, 2009(actual)
Against the original forecast
- Construction start2 months lateforecast May 1, 2009
- Construction end7 months earlyforecast Mar 31, 2010