Columbia Avenue Sidewalk
Radium Hot Springs, British Columbia
Federal contribution
$10,000
Federal share25%
of $40.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 13, 2009
ApprovedAug 10, 2009
Built
Approved 5 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Village of Radium Hot Springs
- Construction start
- Jul 31, 2009(actual)
- Construction end
- Oct 1, 2009(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 1, 2009
- Construction end6 months earlyforecast Mar 31, 2010