Water Reservoir Replacement
Radium Hot Springs, British Columbia
Federal contribution
$600,000
Federal share50%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 30, 2016
201720182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Radium Hot Springs
- Construction start
- Sep 12, 2017(actual)
- Construction end
- Dec 31, 2018(actual)
Against the original forecast
- Construction start5 months lateforecast Apr 24, 2017
- Construction end2 months lateforecast Oct 31, 2018
Also in Radium Hot Springs
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47697 in the federal list. How to read these figures.