Back to projects

Sinclair Creek Trail Connectors

Radium Hot Springs, British Columbia

completeActive TransportationNRT
Federal contribution
$30,000
Federal share50%

of $60.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 30, 2009
2010
Built

Approved 2 months before the announcement.

Program
National Recreational Trails Program
Construction start
May 26, 2009(actual)
Construction end
Mar 31, 2010(actual)

Also in Radium Hot Springs

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50972 in the federal list. How to read these figures.