One Mile Lake Accessible Trail Improvements
Federal contribution
$20,000
Federal share25%
of $80.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 13, 2009
ApprovedAug 10, 2009
Built
Approved 5 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Village of Pemberton
- Construction start
- Aug 31, 2009(actual)
- Construction end
- Dec 15, 2009(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 1, 2009
- Construction end3 months earlyforecast Mar 31, 2010
Also in Pemberton
- Pemberton - Water Treatment Plant$3.3M
- Pemberton - Valley Soccer Field and Amenity Building$1.7M
- Lilwat Nation- Lilwat Health & Healing Centre Renovation$1.2M
- Pemberton - Regional Multi-Modal Transportation Hub - Phase 1$742.7K
- Village of Pemberton to Lil'wat Nation Friendship Trail: Pemberton Farm Road East Connector$418.2K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29382 in the federal list. How to read these figures.