Back to projects

Pier 30 Rehabilitation

Sept-Îles, Quebec

completeMarineISF
Federal contribution
$4.3M
$4,345,997
Federal share48%

of $9.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 20, 2009
ApprovedOct 16, 2009
20102011
Built

Approved 3 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Sept-Îles Port Authority
Construction start
Jul 20, 2009(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2009
  • Construction end4 weeks lateforecast Sep 30, 2011

Also in Sept-Îles

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29406 in the federal list. How to read these figures.