Pier 30 Rehabilitation
Federal contribution
$4.3M
$4,345,997
Federal share48%
of $9.1M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 20, 2009
ApprovedOct 16, 2009
20102011
Built
Approved 3 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Sept-Îles Port Authority
- Construction start
- Jul 20, 2009(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start3 months lateforecast May 1, 2009
- Construction end4 weeks lateforecast Sep 30, 2011
Also in Sept-Îles
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29406 in the federal list. How to read these figures.