Pavement Reconstruction on Route 138 in Sept-Îles (Phase 4)
Federal contribution
$670,917
Federal share50%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 3, 2010
Built
Approved 4 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Aug 23, 2010(actual)
- Construction end
- Oct 8, 2010(actual)
Against the original forecast
- Construction start8 weeks lateforecast Jul 1, 2010
- Construction end3 weeks earlyforecast Oct 31, 2010
Also in Sept-Îles
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 38896 in the federal list. How to read these figures.