Port of Sept-Îles Terminal de la Relance
Federal contribution
$14.9M
$14,939,157
Federal share50%
of $30.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 8, 2009
ApprovedOct 16, 2009
20102011
Built
Approved 5 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Sept-Îles Port Authority
- Construction start
- Mar 8, 2010(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start5 months lateforecast Oct 1, 2009
Also in Sept-Îles
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33175 in the federal list. How to read these figures.