Improving Public Access to the Port of Trois-Rivières

Trois-Rivières, Quebec

completeMarineISF
Federal contribution
$216,137
Federal share44%

of $486.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedNov 2, 2009
20102011
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Sep 1, 2010(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction end3 months earlyforecast Jun 30, 2011