Pipeline Road West Water Transmission Main

Saint John, New Brunswick

completeDrinking WaterISF
Federal contribution
$1.5M
$1,518,582
Federal share32%

of $4.7M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 17, 2009
ApprovedJul 28, 2010
2010
Built

Approved 11 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Saint John
Construction start
Apr 1, 2010(actual)
Construction end
Aug 6, 2010(actual)

Against the original forecast

  • Construction end8 months earlyforecast Mar 31, 2011

Also in Saint John

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29478 in the federal list. How to read these figures.