Dever Road - Watermain

Saint John, New Brunswick

completeDrinking WaterISF
Federal contribution
$1.3M
$1,300,000
Federal share33%

of $3.9M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 17, 2009
ApprovedJul 28, 2010
20102011
Built

Approved 11 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Saint John
Construction start
Jun 21, 2010(actual)
Construction end
Dec 23, 2010(actual)

Against the original forecast

  • Construction end3 months earlyforecast Mar 31, 2011