District metering - Saint John

Saint John, New Brunswick

completeDrinking WaterISF
Federal contribution
$455,446
Federal share33%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 17, 2009
ApprovedJul 28, 2010
20102011
Built

Approved 11 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Saint John
Construction start
Sep 13, 2010(actual)
Construction end
Mar 9, 2011(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Aug 23, 2010
  • Construction end3 weeks earlyforecast Mar 31, 2011