Gunn Road Upgrade
Federal contribution
$2.1M
$2,067,763
Federal share28%
of $7.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 22, 2009
201020112012
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Winnipeg
- Construction start
- Feb 9, 2010(actual)
- Construction end
- Feb 28, 2012(actual)
Against the original forecast
- Construction start8 weeks lateforecast Dec 15, 2009
Also in Winnipeg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29515 in the federal list. How to read these figures.