Manitoba Centennial Centre Refurbishment
Federal contribution
$2.5M
$2,500,000
Federal share50%
of $5.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 29, 2009
20102011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Manitoba Centennial Centre Corporation
- Construction start
- Sep 30, 2009(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction end3 weeks lateforecast Oct 9, 2011
Also in Winnipeg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29518 in the federal list. How to read these figures.