Water system on Hénault Street
Notre-Dame-des-Prairies, Quebec
Federal contribution
$31,075
Federal share26%
of $120.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 23, 2010
2010
Built
Approved 11 months before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Notre-Dame-Des-Prairies
- Construction start
- Sep 1, 2009(actual)
- Construction end
- Nov 30, 2009(actual)
Against the original forecast
- Construction end4 months earlyforecast Mar 31, 2010
Also in Notre-Dame-des-Prairies
- Construction of an indoor refrigerated ice rink$1.5M
- Development of the active transportation network - Linking the residential area to the school, recreational, cultural and community perimeter of 3e avenue and Gauthier Nord street in Notre-Dame-des-Pr$835.4K
- Program for the renewal of drinking water and wastewater pipes$653.0K
- Drinking Water Network Extension on Rang Sainte-Julie$290.5K
- Program for the renewal of drinking water and wastewater pipes$241.5K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29553 in the federal list. How to read these figures.