3rd Street South Paving

Coldwell, Manitoba

completeHighways and RoadsISF
Federal contribution
$174,423
Federal share25%

of $705.3K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 11, 2009
ApprovedOct 6, 2009
2010
Built

Approved 4 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
May 17, 2010(actual)
Construction end
Jun 9, 2010(actual)

Against the original forecast

  • Construction start2 weeks lateforecast May 1, 2010
  • Construction end3 weeks earlyforecast Jun 30, 2010