Rehabilitation of Lundar Arena
Federal contribution
$556,014
Federal share16%
of $3.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 9, 2017
20182019
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Rural Municipality of Coldwell
- Construction start
- Aug 14, 2017(actual)
- Construction end
- Feb 9, 2019(actual)
Against the original forecast
- Construction end4 months lateforecast Sep 30, 2018
Also in Coldwell