Back to projects

Coldwell - Handi-Van Purchase

Coldwell, Manitoba

completePublic TransitPTIF
Federal contribution
$28,122
Federal share47%

of $60.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
2018
Built

Approved 5 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Aug 23, 2017(actual)
Construction end
Jan 29, 2018(actual)

Against the original forecast

  • Construction start5 months lateforecast Apr 3, 2017
  • Construction end2 months earlyforecast Mar 31, 2018

Also in Coldwell

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49240 in the federal list. How to read these figures.