Maintenance Work at the Félix-Leclerc Concert Hall
Federal contribution
$781,200
Federal share33%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 27, 2009
ApprovedJan 26, 2010
20102011
Built
Approved 5 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Val-d'Or
- Construction start
- Sep 1, 2010(actual)
- Construction end
- May 12, 2011(actual)
Against the original forecast
- Construction end4 weeks earlyforecast Jun 10, 2011
Also in Val-d'Or
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29762 in the federal list. How to read these figures.