Back to projects

Construction of a sports complex

Val-d'Or, Quebec

completeRecreationSCF
Federal contribution
$4.0M
$3,954,925
Federal share33%

of $11.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 20, 2017
2017201820192020
Built

Approved 5 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Val-d'Or
Construction start
Jan 26, 2017(actual)
Construction end
Mar 2, 2020(actual)

Against the original forecast

  • Construction start16 months earlyforecast Jun 4, 2018
  • Construction end4 weeks earlyforecast Mar 31, 2020

Also in Val-d'Or

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47736 in the federal list. How to read these figures.