Extension of the municipal water system along 3rd Avenue West

Val-d'Or, Quebec

completeDrinking WaterCC Top Up
Federal contribution
$541,693
Federal share27%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 26, 2010
2011
Built

Approved 4 weeks before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
City of Val-D'Or
Construction start
Oct 4, 2010(actual)
Construction end
Jul 15, 2011(actual)

Against the original forecast

  • Construction start4 months lateforecast Jun 1, 2010
  • Construction end2 weeks lateforecast Jun 30, 2011

Also in Val-d'Or

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39866 in the federal list. How to read these figures.