Extension of the municipal water system along 3rd Avenue West
Federal contribution
$541,693
Federal share27%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 26, 2010
2011
Built
Approved 4 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- City of Val-D'Or
- Construction start
- Oct 4, 2010(actual)
- Construction end
- Jul 15, 2011(actual)
Against the original forecast
- Construction start4 months lateforecast Jun 1, 2010
- Construction end2 weeks lateforecast Jun 30, 2011
Also in Val-d'Or
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39866 in the federal list. How to read these figures.