Kicking Horse Canyon - Golden Hill to West Portal

Golden, British Columbia

completeHighways and RoadsMIC
Federal contribution
$23.1M
$23,143,057
Federal share50%

of $46.3M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedNov 6, 2007
ApprovedAug 6, 2008
2008201020122014
Built

Approved 9 months after the announcement.

Program
Building Canada Fund - Major Infrastructure Component
Construction start
Oct 1, 2008(actual)
Construction end
Jun 30, 2014(actual)

Against the original forecast

  • Construction end21 months lateforecast Sep 30, 2012

Also in Golden

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29842 in the federal list. How to read these figures.