Back to projects

Repairs to water treatment plant

Sainte-Catherine, Quebec

completeWastewaterCC
Federal contribution
$6.0M
$5,968,719
Federal share39%

of $15.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
20102012201420162018
Built

Approved 6.5 years before the announcement.

Program
Building Canada Fund - Communities Component
Construction start
Feb 2, 2011(actual)
Construction end
Oct 30, 2018(actual)

Against the original forecast

  • Construction start18 months lateforecast Jul 30, 2009
  • Construction end7.6 years lateforecast Mar 31, 2011

Also in Sainte-Catherine

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29855 in the federal list. How to read these figures.