Construction of a Multi-use Pathway on Lamarche Street between Marie-Victorin Boulevard and Providence Park, in Sainte-Catherine

Sainte-Catherine, Quebec

completeActive TransportationATF
Federal contribution
$511,359
Federal share49%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 12, 2025
202320242025
Built

Approved 2.3 years before the announcement.

Program
Active Transportation Fund
Construction start
Apr 17, 2023(actual)
Construction end
Jul 31, 2024(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast May 23, 2023
  • Construction end9 months lateforecast Oct 27, 2023