Water Systems Upgrades

Sainte-Catherine, Quebec

completeDrinking WaterGIS
Federal contribution
$540,725
Federal share40%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
20212022
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Construction start
May 24, 2021(actual)
Construction end
Oct 28, 2022(actual)