Pictou County Wellness Centre
Federal contribution
$10.6M
$10,576,887
Federal share33%
of $31.7M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 27, 2009
ApprovedJul 16, 2010
2010201120122013
Built
Approved 16 months after the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Pictou County Wellness Centre Building Authority Incorporated
- Construction start
- Aug 8, 2010(actual)
- Construction end
- Dec 3, 2012(actual)
Also in Pictou
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29866 in the federal list. How to read these figures.