Pictou County Wellness Centre

Pictou, Nova Scotia

completeRecreationMIC
Federal contribution
$10.6M
$10,576,887
Federal share33%

of $31.7M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 27, 2009
ApprovedJul 16, 2010
2010201120122013
Built

Approved 16 months after the announcement.

Program
Building Canada Fund - Major Infrastructure Component
Construction start
Aug 8, 2010(actual)
Construction end
Dec 3, 2012(actual)