Boat Harbour Remediation
Federal contribution
$100.0M
$100,000,000
Federal share22%
of $445.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2019
today
201920222025202820312034
BuiltForecast
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Province of Nova Scotia
- Construction start
- Sep 1, 2027(forecast)
- Construction end
- Oct 31, 2033(forecast)
Also in Pictou
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52972 in the federal list. How to read these figures.