Upper Plymouth/McLellan's Brook Wastewater Project Phase II
Federal contribution
$3.6M
$3,557,536
Federal share49%
of $7.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 16, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of the County of Pictou
- Construction start
- Dec 5, 2016(actual)
- Construction end
- Jan 29, 2018(actual)
Against the original forecast
- Construction start3 months lateforecast Sep 1, 2016
- Construction end2.2 years earlyforecast Mar 31, 2020
Also in Pictou
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47241 in the federal list. How to read these figures.