Ottawa River Action Plan
Federal contribution
$33.0M
$33,000,000
Federal share50%
of $66.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 22, 2010
2010201220142016
Built
Approved 8 months before the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- City of Ottawa
- Construction start
- Jun 5, 2009(actual)
- Construction end
- Oct 12, 2016(actual)
Against the original forecast
- Construction end3 months earlyforecast Dec 31, 2016
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29902 in the federal list. How to read these figures.