Winnipeg SEWPCC Wet Weather Treatment
Federal contribution
$11.0M
$11,000,000
Federal share26%
of $42.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 26, 2014
20142017202020232026
Built
Approved 6 months before the announcement.
- Program
- Green Infrastructure Fund
- Ultimate recipient
- City of Winnipeg
- Construction start
- Sep 1, 2014(actual)
- Construction end
- Feb 27, 2026(actual)
Against the original forecast
- Construction start5 months lateforecast Mar 31, 2014
- Construction end5 weeks earlyforecast Mar 31, 2026
Also in Winnipeg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29905 in the federal list. How to read these figures.