Public Works Building Rehabilitation - Cambridge

Cambridge, Ontario

completeAdministration, Emergency and Public WorksISF
Federal contribution
$1.4M
$1,400,000
Federal share33%

of $4.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Cambridge
Construction start
Jul 20, 2009(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jul 2, 2009