Upgrade of the Galt Wastewater Treatment Plant Digester
Federal contribution
$1.5M
$1,513,521
Federal share25%
of $6.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional Municipality of Waterloo
- Construction start
- Mar 15, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start9 months earlyforecast Nov 30, 2010
Also in Cambridge
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30341 in the federal list. How to read these figures.