B-Line Road Resurfacing
North Algona Wilberforce, Ontario
Federal contribution
$115,000
Federal share33%
of $345.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of North Algona Wilberforce
- Construction start
- Oct 5, 2009(actual)
- Construction end
- Oct 23, 2009(actual)
Against the original forecast
- Construction end2 months earlyforecast Dec 31, 2009