Golden Lake Municipal Building Rehabilitation

North Algona Wilberforce, Ontario

completeAdministration, Emergency and Public WorksISF
Federal contribution
$14,336
Federal share27%

of $54.0K total eligible cost; the rest comes from other partners.

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jul 14, 2009(actual)
Construction end
Sep 2, 2009(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Aug 1, 2009