Rehabilitation of Letts Cemetery Road

North Algona Wilberforce, Ontario

completeHighways and RoadsRNIS
Federal contribution
$580,852
Federal share60%

of $968.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 22, 2019
202020212022
Built
Program
Rural & Northern Infrastructure Stream
Construction start
Jun 28, 2021(actual)
Construction end
Oct 11, 2022(actual)

Against the original forecast

  • Construction start13 months lateforecast Jun 1, 2020
  • Construction end3 months lateforecast Jun 30, 2022