Rehabilitation of Letts Cemetery Road
North Algona Wilberforce, Ontario
Federal contribution
$580,852
Federal share60%
of $968.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 22, 2019
202020212022
Built
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Township of North Algona Wilberforce
- Construction start
- Jun 28, 2021(actual)
- Construction end
- Oct 11, 2022(actual)
Against the original forecast
- Construction start13 months lateforecast Jun 1, 2020
- Construction end3 months lateforecast Jun 30, 2022