Big Bay Culvert Replacement

Georgian Bluffs, Ontario

completeHighways and RoadsISF
Federal contribution
$55,000
Federal share33%

of $165.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Georgian Bluffs
Construction start
Jun 17, 2009(actual)
Construction end
Oct 8, 2009(actual)

Against the original forecast

  • Construction end5 weeks lateforecast Aug 31, 2009

Also in Georgian Bluffs

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30347 in the federal list. How to read these figures.