Line 86 Rehabilitation
Federal contribution
$522,373
Federal share33%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional Municipality of Waterloo
- Construction start
- Aug 31, 2009(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 1, 2009
Also in Woolwich
- West Montrose Covered Bridge Rehabilitation$2.5M
- Rehabilitation of the Weigel Stormwater Management Drain$899.9K
- Woolwich Memorial Centre - Refrigeration Plant and Dehumidifier Replacement$792.0K
- Regional Road 22 (Northfield Drive) from Line 86 to Waterloo/Wellington Boundary$723.0K
- Rehabilitation of the Glasgow Street South Bridge in Conestogo$704.4K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30396 in the federal list. How to read these figures.