Rehabilitation of the Glasgow Street South Bridge in Conestogo
Federal contribution
$704,375
Federal share50%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 19, 2019
2020202120222023
Built
Approved 4 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Township of Woolwich
- Construction start
- Aug 16, 2021(actual)
- Construction end
- Mar 29, 2023(actual)
Against the original forecast
- Construction end7 months earlyforecast Oct 31, 2023
Also in Woolwich
- West Montrose Covered Bridge Rehabilitation$2.5M
- Rehabilitation of the Weigel Stormwater Management Drain$899.9K
- Woolwich Memorial Centre - Refrigeration Plant and Dehumidifier Replacement$792.0K
- Regional Road 22 (Northfield Drive) from Line 86 to Waterloo/Wellington Boundary$723.0K
- Line 86 Rehabilitation$522.4K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54197 in the federal list. How to read these figures.