Rehabilitation of the Weigel Stormwater Management Drain

Woolwich, Ontario

underwayWastewaterGIS
Federal contribution
$899,928
Federal share40%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 23, 2021
today
2021202320252027
BuiltForecast

Approved 8 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Township of Woolwich
Construction start
Jun 2, 2025(actual)
Construction end
Oct 16, 2026(forecast)