Rehabilitation of the Weigel Stormwater Management Drain
Federal contribution
$899,928
Federal share40%
of $2.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 23, 2021
today
2021202320252027
BuiltForecast
Approved 8 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Township of Woolwich
- Construction start
- Jun 2, 2025(actual)
- Construction end
- Oct 16, 2026(forecast)
Also in Woolwich
- West Montrose Covered Bridge Rehabilitation$2.5M
- Woolwich Memorial Centre - Refrigeration Plant and Dehumidifier Replacement$792.0K
- Regional Road 22 (Northfield Drive) from Line 86 to Waterloo/Wellington Boundary$723.0K
- Rehabilitation of the Glasgow Street South Bridge in Conestogo$704.4K
- Line 86 Rehabilitation$522.4K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57396 in the federal list. How to read these figures.