Port Sydney Fire Hall
Federal contribution
$400,000
Federal share33%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Huntsville
- Construction start
- Oct 1, 2009(actual)
- Construction end
- Jun 1, 2010(actual)
Against the original forecast
- Construction start2 weeks lateforecast Sep 14, 2009
- Construction end2 months lateforecast Mar 30, 2010
Also in Huntsville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30529 in the federal list. How to read these figures.