Upgrades to the Ferguson Pumping Station
Federal contribution
$6.7M
$6,666,017
Federal share33%
of $20.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
201020112012
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Hamilton
- Construction start
- Feb 5, 2010(actual)
- Construction end
- Aug 31, 2012(actual)
Against the original forecast
- Construction start2 months lateforecast Nov 30, 2009