Back to projects

Kenilworth Water Reservoir and Pumping Station Upgrades

Hamilton, Ontario

completeDrinking WaterISF
Federal contribution
$2.3M
$2,266,667
Federal share33%

of $6.8M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
201020112012
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Hamilton
Construction start
Nov 22, 2010(actual)
Construction end
Nov 28, 2011(actual)

Against the original forecast

  • Construction start3 months lateforecast Sep 1, 2010
  • Construction end4 weeks lateforecast Oct 31, 2011

Also in Hamilton