Stone Church Water Reservoir and Pumping Station Upgrades
Federal contribution
$1.5M
$1,500,000
Federal share33%
of $4.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
201020112012
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Hamilton
- Construction start
- Nov 22, 2010(actual)
- Construction end
- Feb 28, 2012(actual)
Against the original forecast
- Construction start3 months lateforecast Sep 1, 2010
- Construction end2 weeks lateforecast Feb 13, 2012
Also in Hamilton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30566 in the federal list. How to read these figures.