Ferguson Subdivision
Federal contribution
$118,324
Federal share26%
of $450.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Cochrane
- Construction start
- Jul 13, 2009(actual)
- Construction end
- Mar 31, 2011(actual)
Also in Cochrane
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30594 in the federal list. How to read these figures.