New Municipal Public Works Garage
Federal contribution
$288,733
Federal share33%
of $866.2K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Schreiber
- Construction start
- Jun 1, 2010(actual)
- Construction end
- Oct 31, 2011(actual)